Unit | Type | Thermal power |
Electric power |
Status (3/2011) |
Start- up |
Shut- down |
Accidents assessed |
Results | |
1 | PWR KWU 3-loop | 2497 MW | 840 MW | permanent shutdown | 1976 | 2011 | SGTR | contamination and dose |
risk per NPP unit |
2 | PWR KWU 4-loop (Convoi) | 3850 MW | 1400 MW | in operation | 1989 | exp. 2036 | ISLOCA | contamination and dose |
risk per NPP unit |